The Crystal Room in Foggy Bottom will be dedicated December 9th after the 11 AM Mass. If possible to schedule with subcontractors we will pour epoxy floors in the kitchen and caterer’s prep area; and failing that, white Vinyl tile, non-slip. Water service will be shut down next Thursdays from 6 Am to Noon. Tile for the flooring arrives Monday. We will use 3x6 “subway” tile on the walls of the kitchen and caterer’s prep area. We are planning to have our occupancy permit a week before dedication . Monday we meet with the sound system contractor. This past week, our entrance roof and extended areas were replaced because they were failing. Things are going well.

 